The Australian Energy Regulator (AER) has received revenue proposals from TransGrid and Murraylink.

TransGrid’s proposal is for its NSW electricity transmission network for the five year period commencing on 1 July 2018. The proposal sets out the revenue TransGrid proposes to collect from NSW electricity consumers through transmission charges from 2018 to 2023.

Murraylink’s proposal is for its interconnector between the Victorian and South Australian networks. The proposal sets out the revenue Murraylink proposes to collect from electricity consumers through charges from 2018 to 2023.

Invitation for submissions

Interested parties are invited to make submissions on the regulatory proposals by the close of business on 12 May 2017.

The AER prefers that all submissions be publicly available to facilitate an informed and transparent consultative process. The AER will treat submissions as public documents unless otherwise requested. Parties wishing to submit confidential information are requested to:

  • clearly identify the information that is the subject of the confidentiality claim
  • provide a non-confidential version of the submission in a form suitable for publication.

All non-confidential submissions will be placed on the AER’s website. For further information regarding the AER’s use and disclosure of information provided to it, see the ACCC/AER Information Policy.

Public forums

We are holding public forums on these regulatory proposals. The TransGrid public forum will be held in Sydney on 11 April 2017. The Murraylink public forum will be held in Adelaide on 10 April 2017. We intend to publish an issues paper on these regulatory proposals prior to the public forums. The issues papers and public forum agendas will be available on our website prior to the public forums.

Interested parties who wish to attend these public forums are encouraged to register by 17 March 2017 by email to:

  • TransGrid: TransGrid2018ataer [dot] gov [dot] au (TransGrid2018[at]aer[dot]gov[dot]au)
  • Murraylink: Murraylink2018ataer [dot] gov [dot] au (Murraylink2018[at]aer[dot]gov[dot]au)

TransGrid - Sydney

Location: Level 20, 175 Pitt Street, Sydney NSW (Note: location may change depending on level of interest)

Date: 11 April 2017

Time: Registration from 2 pm. Public forum to commence at 2.15 pm and conclude by 4.15 pm.

Telephone: (02) 9230 9133

Murraylink - Adelaide

Location: Level 2, 19 Grenfell Street, Adelaide SA

Date: 10 April 2017

Time: Registration from 11.45 am. Public forum to commence at 12 noon and conclude by 2 pm.

Telephone: (08) 8213 3444