Results
52 result(s), displaying 25 to 36
Powercor - Determination 2026–31
Powercor is an electricity distribution network service provider. Its next five year regulatory control period will be 1 July 2026 to 30 June 2031.
Type
Determinations
Status
Open
United Energy - Determination 2026–31
United Energy is an electricity distribution network service provider. Its next five year regulatory control period will be 1 July 2026 to 30 June 2031.
Type
Determinations
Status
Open
AusNet Services - Cost pass through - October 2021 storm
On 22 June 2022, the AER released its determination on AusNet Services' October 2021 storm cost pass through application.
Type
Cost pass throughs
Status
Open
AusNet Services – Cost pass through - June 2021 storms natural disaster
On 16 March 2022, the AER released its determination on AusNet Services' cost pass through application.
Type
Cost pass throughs
Status
Open
TransGrid – Expanding Victoria-New South Wales transmission transfer capacity contingent project
Type
Contingent projects
Status
Open
Powercor - Contingent project - installation of Rapid Earth Fault Current Limiters - tranche 3
Type
Contingent projects
Status
Open
Marinus Link - Determination 2025-28 - Stage 1, Part A (Early works)
The AER’s role is to review the reasonableness of the proposed costs of the Marinus Link interconnector to ensure consumers pay no more than necessary.
Type
Determinations
Status
Open
Jemena - Determination 2021-26
In 2024 Jemena applied to the AER to revoke and substitute its distribution determination for the 2021-26 regulatory control period.
Type
Determinations
Status
Open
Victoria: December 2026 - February 2027
The Retailer Reliability Obligation (RRO) is designed to support reliability in the National Electricity Market (NEM).
Type
Retail Reliability Obligation
Status
Open
CitiPower, Powercor, and United Energy - Ring-fencing waiver - Electric vehicle charging infrastructure
The AER invites stakeholders to provide feedback on CPU’s application for a waiver from the Ringfencing guideline (electricity distribution) to provide EVCI.
Type
Ring-fencing
Status
Open