NSW Electricity Infrastructure Roadmap - contribution determination 2024−25
View our decision on the maximum amount electricity distributors can pass through to consumers in 2024-25 as costs for the NSW infrastructure roadmap.
Type
Cost pass throughs
Status
Current
Essential Energy - Ring-fencing waiver - training services
Essential Energy submitted a ring-fencing waiver application under clause 5.2 of the Electricity Distribution Ring-fencing Guideline.
Type
Ring-fencing
Status
Open
Essential Energy - Ring-fencing waiver - November 2023
Essential Energy waiver for its Water supply business in regional NSW - November 2023
Type
Ring-fencing
Status
Current
Evoenergy - Ring-fencing waiver - November 2023
The ring-fencing waiver granted to Evo energy to continue offering gas supply services in ACT region.
Type
Ring-fencing
Status
Current
Jemena - Determination 2026–31
Jemena is an electricity distribution network service provider. Its next five year regulatory control period will be 1 July 2026 to 30 June 2031.
Type
Determinations
Status
Open
CitiPower - Determination 2026–31
CitiPower is an electricity distribution network service provider. Its next five year regulatory control period will be 1 July 2026 to 30 June 2031.
Type
Determinations
Status
Open
Powercor - Determination 2026–31
Powercor is an electricity distribution network service provider. Its next five year regulatory control period will be 1 July 2026 to 30 June 2031.
Type
Determinations
Status
Open
United Energy - Determination 2026–31
United Energy is an electricity distribution network service provider. Its next five year regulatory control period will be 1 July 2026 to 30 June 2031.
Type
Determinations
Status
Open
AusNet Services - Determination 2026–31
AusNet Services is an electricity distribution network service provider. Its next five year regulatory control period will be 1 July 2026 to 30 June 2031.
Type
Determinations
Status
Open
Essential Energy - Cost pass through - 2022 north coast flood event
On 30 March 2023, the AER released its determination on Essential Energy’s 2022 North Coast flooding cost pass through application.
Type
Cost pass throughs
Status
Current
Powercor - Cost pass through - Increase to minimum wood pole interventions
Type
Cost pass throughs
Status
Current
AusNet Services - Cost pass through - October 2021 storm
On 22 June 2022, the AER released its determination on AusNet Services' October 2021 storm cost pass through application.
Type
Cost pass throughs
Status
Open